Summary of Findings:
Plan not certified by a professioal engineer.
Inspections and tests required by 40 CFR Part 112 are not in accordance with written procedures developed for the facility.
Written procedures and inspection records are not signed by appropriate supervisor or inspector, are not kept with the plan and are not maintained for three years.
Spill prevention briefings are not scheduled and conducted periodically.