Administrative - Formal · FY2009 · — · Final Order With Penalty · 1400027685

Penalty
Cost recovery
Compliance action

Case

Case Number
04-2009-8005
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
Self-disclosure
N

Defendants (1)

Summary

1/23/09 - EXPEDITED SETTLEMENT AGREEMENT ISSUED, ASSESSING A PENALTY OF #360, DUE WITHIN 15 DAYS. ALLEGED VIOLATIONS: BASED ON A COMPLIANCE MONITORING INSPECTION CONDUCTED AT THE RESPONDENT'S FACILITY LOCATED ON BENEFIELD ROAD, EVERGREEN, AL, ON DEC 6, 2007, EPA ALLEGES THAT THE RESPONDENT VIOLATED THE CAA'S CHEMICAL ACCIDENT PREVENTION PROGRAM WHEN RESPONDENT DID NOT PROVIDE EVIDENCE THAT: IT HAS PREPARED WRITTEN PROCEDURES TO MAINTAIN THE ON-GOINING MECHANICAL INTEGRITY OF PROCESS EQUIPMENT AS REQUIRED BY 40 CFR 68.56(a).