2/17/05 - COMPLIANCE ORDER ISSUED. VIOLATIONS: FAILURE TO COMPLY WITH THE FOLLOWING PERMIT CONDITIONS: PART III.C.2; PART III.C.3; PART IV(i); PART IV.D.2.a(1); PART IV.D.2.a(3); PART IV.D.3.a(4); AND PART V.L.
ORDER REQUIRES:
A. IMMEDIATELY, RESPONDENT SHALL PROVIDE SILT FENCES OR OTHER EQUIVALENT STRUCTURAL PRACTICES ON ALL EXPOSED AREAS OF THE FACILITY. WITHIN 14 DAYS, RESPONDENT SHALL PROVIDE WRITTEN CERTIFICATION DESCRIBING THE PERIMETER STRUCTURES IT HAS PROVIDED, INCLUDING LOCATIONS.
B. WITHIN 7 DAYS, RESPONDENT SHALL IMPLEMENT MAINTENANCE PROVISIONS AT ITS FAICLITY TO ENSURE THE TIMELY MAINTENANCE OF VEGETATION, EROSION, AND SEIDMENT CONTROLS, STORMWATER MANAGEMENT PRACTICES, AND OTHER PROTECTIVE MEASURES AND BMPs SO THEY WILL REMAIN IN GOOD AND EFFECTIVE OPERATING CONDITION BY REPAIRING/MAINTAINING SILT FENCING, OUTFALL AND CURB INLET PROTECTION AND CONSTRUCTION ENTRANCES AND EXITS THROUGHOUT THE SITE AND PROVIDING TEMPORARY STABILIZATION WHERE NECESSARY. WITHIN 14 DAYS, RESPONDENT SHALL PROVIDE WRITTEN CERTIFICATION DESCRIBING THE CONTROLS IT HAS IMPLEMENTED, INCLUDING LOCATIONS.
C. WITHIN 14 DAYS, RESPONDENT SHALL PROVIDE SOIL STABILIZATION ON AREAS WHERE CONSTRUCTION ACTIVITIES HAVE TEMPORARILY OR PERMANENTLY CEASED AT ITS FACILITY. WITHIN 14 DAYS, RESPONDENT SHALL PROVIDE WRITTEN CERTIFICATION DESCRIBING THE STABILIZATION MEASURES IT HAS PROVIDED, INCLUDING LOCATIONS.
D. WITHIN 30 DAYS, RESPONDENT SHALL MODIFY THE ESPCP, IF NECESSARY, AS