# GOODYEAR TIRE & RUBBER COMPANY
> **Administrative - Formal** · FY2005 · — · Final Order No Penalty
## Case
- **Activity ID:** `142993`
- **Case Number:** 07-2005-0195
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order No Penalty
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- GOODYEAR TIRE & RUBBER COMPANY (complaint) (settlement)
## Summary

RESPONDENT COMMENCED CONSTRUCTION OF BOILER NO. 5 ON OR ABOUT APRIL 2, 1988, AND BEGAN OPERATING THE BOILER ON OR ABOUT FEBRUARY 1, 1989.  BASED ON INFORMATION SUBMITTED BY GOODYEAR SULFUR DIOXIDE EMISSIONS FROM THE BOILER TRIGGERED PREVENTION OF SIGNIFICANT DETERIORATION REVIEW.

---
*Source: [EPA ECHO](https://echo.epa.gov/) · AI Analytics · CC0 1.0*