← EPA enforcement cases

Hot Asphalt Paving

Administrative - Formal · FY2005 · — · Unilateral Administrative Order Without Adjudication · 143769

Penalty
Cost recovery
Compliance action

Case

Case Number
02-2005-3183
Type
Administrative - Formal
Lead
EPA
Outcome
Unilateral Administrative Order Without Adjudication
Multimedia
Self-disclosure
N

Defendants (1)

Summary

THis construction site is located on steep slopes, HAPI has a road widening and improvement project from Km 37.0 to 53.2 on PR-123. at Km. 40.4 excavation assocated with a slope stablization project was seen. This site is over 1 acre, but no construction permit has been filed.

Source

Authoritative
EPA ECHO
Machine
JSON-LD · Markdown