← EPA enforcement cases

PORT OF TACOMA OCCIDENTAL CHEMICAL

Judicial · FY2005 · — · Final Order No Penalty · 144538

Penalty
Cost recovery
Compliance action

Case

Case Number
10-2005-0146
Type
Judicial
Lead
EPA
Outcome
Final Order No Penalty
Multimedia
Self-disclosure
N

Defendants (4)

Summary

PURSUANT TO THIS CONSENT DECREE, THE PORT, OCCIDENTAL, MARIANA, AND PIONEER WILL PERFORM RD/RA FOR THE MOUTH OF THE HYLEBOS WATERWAY PROBLEM AREA AND REIMBURSE THE U.S. FOR FUTURE OVERSIGHT COST. ESTIMATED VALUE OF WORK IS $36.5 MILLION.

Source

Authoritative
EPA ECHO
Machine