# AMERICAN BLUEGRASS MARBLE COMPANY
> **Administrative - Formal** · FY2005 · — · Unilateral Administrative Order Without Adjudication
## Case
- **Activity ID:** `148407`
- **Case Number:** 04-2005-1830
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Unilateral Administrative Order Without Adjudication
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- AMERICAN BLUEGRASS MARBLE COMPANY (SB) (settlement)
## Summary

5/19/05 - COMPLIANCE ORDER ISSUED.  ACCORDING TO INFORMATION PROVIDED BY THE LOUISVILLE METRO AIR POLLUTION CONTROL DISTRICT (LMAPCD), THE ANNUAL COMPLIANCE CERTIFICATION WAS DUE TO THE ADMINISTRATOR OF EPA REGION IV BY APRIL 15, 2005.  ACCORDING TO EPA RECORDS FOR COMPLIANCE CERTIFICATIONS, AS OF MAY 19, 2005, RESPONDENT HAS NOT SUBMITTED A COMPLIANCE CERTFICIATION TO THE REGIONAL ADMINISTRATOR OF EPA, REGION 4.  

ORDER REQUIRES:  RESPONDENT SHALL SUBMIT TO THE ADMINISTRATOR OF EPA REGION, A CERTIFICATION OF COMPLIANCE WITH PERMIT TERMS AND CONDITIONS IN ACCORDANCE WITH 40 CFR 70.6(c)(5), INLCUDING EMISSION LIMITATIONS, STANDARDS OR WORK PRACTICES FOR THE CALENDAR YEAR 2004 WITHIN 14 DAYS

---