6/21/05 - ADMINISTRATIVE ORDER ISSUED.
VIOLATIONS:
1. PARTS I.A.2; I.C.1; I.C.2; II.B.1; AND II.C.2 OF THE PERMIT BY FAILING TO IMPLEMENT THE EROSION AND SEDIMENTATION CONTROL PLAN AS APPROVED AND OPERATE AND MAINTAIN ALL EROSION AND SEDIMENTATION CONTROL FACILITIES.
2. PARTS I.B.2; II.B.1; AND II.B.2 OF THE PERMIT BY FAILING TO TAKE CORRECTIVE ACTION IMMEDIATELY TO CONTROL THE DISCHARGE OF SEDIMENTS.
3. PARTS I.B.1; I.B.2; I.B.3; AND II.B.1 OF THE PERMIT BY FAILING TO PROPERLY INSPECT AND KEEP A RECORD OF THE EROSION AND SEDIMENT CONTROL FACILITY INSPECTIONS.
ORDER REQUIRES:
IMMEDIATELY BEGIN INSPECTING ALL EROSION AND SEDIMENTATION CONTROL FACILITIES AND STORM WATER RUNOFF DISCHARGES AT LEAST ONCE EVERY 7 CALENDAR DAYS AND WITHIN 24 HOURS AFTER ANY STORM EVENT GREATER THAN 0.5 INCHES PER 24-HOUR PERIOD; MAINTAIN A RAIN GAUGE ON THE SITE AND RECORD RAINFALL AMOUNTS AND DATES. EVERY 30 CALENDAR DAYS, FOR A PERIOD OF 90 DAYS, SUBMIT COPIES OF SUCH INSPECTION REPORTS AND RAINFALL DATA.
IMMEDIATELY TAKE CORRECTIVE ACTION TO CONTROL THE DISCHARGE OF VISIBLE SEDIMENTS LEAVING THE DISTURBED LIMITS OF THE SITE; SPECIFICALLY, PROVIDE SLOPE STABILIZATION AND CHECK DAM MAINTENANCE. WITHIN 30 DAYS, SUBMIT DOCUMENTATION THAT THIS REQUIREMENT OF THE ORDER HAS BEEN MET.
IMMEDIATELY BEGIN KEEPING A RECORD OF INSPECTIONS, INCLUDING VISIBLE SEDIMENTATION FOUND OUTSIDE THE DISTURBED LIMITS OF THE SITE, AN EXPLANATION OF MEASURES TAKEN TO CONTROL FUTURE RELEASES, A