← EPA enforcement cases

ROHM & HAAS COMPANY

Judicial · FY1990 · — · Final Order With Specified Cost Recovery · 15098

Penalty
$250K
Cost recovery
Compliance action

Case

Case Number
03-1990-0623
Type
Judicial
Lead
EPA
Outcome
Final Order With Specified Cost Recovery
DOJ Docket
90-11-3-701
Multimedia
N
Self-disclosure
N

Defendants (6)

Summary

THIS IS AN ACTION UNDER CERCLA 107 TO RECOVER OVER $4 MILLION IN RESPONSE COSTS INCURRED AT THE WHITMOYER SITE AND TO MOVE FOR DECLARATORY JUDGEMENT AGAINST ALL PRP'S FOR FUTURE RESPONSE COSTS

Source

Authoritative
EPA ECHO
Machine