Western Shopping Center Norte, Inc.

Administrative - Formal · FY2005 · — · Unilateral Administrative Order Without Adjudication · 151044

Penalty
Cost recovery
Compliance action

Case

Case Number
02-2005-3501
Type
Administrative - Formal
Lead
EPA
Outcome
Unilateral Administrative Order Without Adjudication
Multimedia
Self-disclosure
N

Defendants (2)

Summary

Unauthorized discharge of fill into 1.9 acres of wetlands for construction of an industrial park. Consent Order requires creation of 10 acres of replacement wetlands and preservation of 10 acres of existing wetlands as compensatory mitigation.