← EPA enforcement cases

DYERSBURG, TN, CITY OF

Administrative - Formal · FY2005 · — · Final Order With Penalty · 152765

Penalty
Cost recovery
Compliance action

Case

Case Number
04-2005-8020
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
Self-disclosure
N

Defendants (1)

Summary

7/19/05 - EXPEDITED SETTLEMENT AGREEMENT ISSUED, ASSESSING A PENALTY OF $4,620. PENALTY PAID. VIOLATIONS: 1. FAILURE TO DOCUMENT AND COMPILE AS PART OF THE PROCESS SAFETY INFORMATION: INFORMATION PERTAINING TO THE TECHNOLOGY OF THE PROCESS: (a) A BLOW FLOW DIAGRAM OR SIMPLIFIED PROCESS FLOW DIAGRAM; (b) MAXIMUM INTENDED INVENTORY (WASTE WATER PLANT ONLY); (c) SAFE UPPER AND LOWER LIMITS FOR SUCH ITEMS AS TEMPERATURE, PRESSURES, FLOWS, AND COMPOSITIONS (WATER WATER PLANT ONLY); AND (d) AN EVALUATION OF THE CONSEQUENCES OF DEVIATIONS. 2. FAILURE TO PERFORM THE PROCESS HAZARD ANALYSIS (PHA) USING A TEAM WITH EXPERTISE IN ENGINEERING AND PROCESS OPERATIONS WHICH INCLUDED ONE MEMBER KNOWLEDGEABLE IN THE SPECIFIC PHA METHODOLOGY THAT WAS USED. 3. FAILURE TO DEVELOP A WRITTEN SCHEDULE OF WHEN PHA ACTION ITEMS WERE TO BE COMPLETED. 4. FAILURE TO DEVELOP WRITTEN OPERATING PROCEDURES WHICH ADDRESS THE FOLLOWING: STEPS FOR EACH OPERATING PHASE: (a) EMERGENCY SHUTDOWN INCLUDING THE CONDITIONS UNDER WHICH EMERGENCY SHUTDOWN IS REQUIRED, AND THE ASSIGNMENT OF SHUTDOWN RESPONSIBILITY TO QUALIFIED OPERATORS TO ENSURE THAT EMERGENCY SHUTDOWN IS EXECUTED IN A SAFE AND TIMELY MANNER (WASTE WATER PLANT ONLY). (b) NORMAL SHUTDOWN (WASTE WATER PLANT ONLY), AND (c) STARTUP FOLLOWING A TURNAROUND, OR AFTER AN EMERGENCY SHUTDOWN (WASTE WATER PLANT ONLY). OPERATING LIMITS: (a) CONSEQUENCES OF DEVIATION (WASTE WATER PLANT ONLY), AND (b) STEPS REQUIRED TO CORRECT

Source

Authoritative
EPA ECHO
Machine