← EPA enforcement cases

SUN COMPANY INC (R&M)

Judicial · FY1992 · — · Final Order With Penalty · 15771

$160K
Penalty
Cost recovery
Compliance action

Case

Case Number
03-1992-0179
Type
Judicial
Lead
EPA
Outcome
Final Order With Penalty
DOJ Docket
90-5-2-1-1731
Multimedia
N
Self-disclosure
N

Defendants (1)

Summary

SUN RECEIVED A WAIVER, FROM EPA, OF COMPLIANCE WITH THE NESHAP FOR BENZENE EMISSIONS FROM BENZENE TRANSFER OPERATION WHICH EXPIRED ON 2/28/92. BEFORE THE EXPIRATION OF THE WAI- VER, SUN APPROACHED EPA AND SAID THAT THE COMPANY WOULD BE UNABLE TO MEET THE FINAL COMPLIANCE DEADLINE BECAUSE THE COAST GUARD (WHO MUST CERIFY SUN'S BENZENE SYSTEM BECAUSE IT INVOLVES LOADING ONTO MARINE VESSELS) WOULD NOT APPROVE THE SYSTEM. SUN ANTICIPATED THAT IT WOULD NEED UNTIL 1/93 IN ORDER TO DEMONSTRATE FINAL COMPLIANCE WITH THE NESHAP. THIS ACTION IS EXPECTED TO RESULT IN A CONSENT DECREE THAT PRO- VIDES A SCHEDULE OF COMPLIANCE AND THE PAYMENT OF A PENALTY. PRN SENT TO DOJ ON 3/23/92. AGREEMENT IN PRINCIPLE REACHED 5/15/92; HOWEVER, PARTIES HAVE NOT BEEN ABLE TO FINALIZE CONSENT AGREEMENT.

Source

Authoritative
EPA ECHO