← EPA enforcement cases

SR 65 MILL AND RESURFACE PROJECT

Administrative - Formal · FY2005 · — · Final Order With Penalty · 159274

Penalty
Cost recovery
Compliance action

Case

Case Number
04-2005-4539
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
Self-disclosure
N

Defendants (1)

Summary

9/30/05 - COMPLAINT FILED PROPOSING A PENALTY OF $157,500. COMPLAINT ALLEGES: RESPONDENT FAILED TO COMPLY WITH PART III.C.2 OF THE PERMIT BY FAILING TO POST A COPY OF THE NOI OR THE PERMIT COVERAGE NOTICE AT THE FACILITY. RESPONDENT FAILED TO COMPLY WITH PART V.C.1 OF THE PERMIT BY FAILING TO AMEND THE STORM WATER POLLUTION PREVENTION PLAN ( SWPPP ) WHEN IT PROVES TO BE INEFFECTIVE IN ELIMINATING OR SIGNIFICANTLY MINIMIZING POLLUTANTS FROM SOURCES TO CONTROL POLLUTANTS FROM SOURCES TO CONTROL POLLUTANTS IN STORM WATER DISCHARGES. RESPONDENT FAILED TO COMPLY WITH PART V.D.1 OF THE PERMIT BY FAILING TO HAVE THE SWPP PROVIDE A DESCRIPTION OF THE INTENDED SEQUENCE OF MAJOR ACTIVITIES WHICH DISTURB SOILS FOR MAJOR PORTIONS OF THE SITE, AND A SITE MAP INDICATING SURFACE WATERS, WETLANDS, AND LOCATIONS WHERE STORM WATER IS DISCHARGED TO A SURFACE WATER. RESPONDENT FAILED TO COMPLY WITH PART V.D.2.a(1) OF THE PERMIT FAILING TO HAVE THE SWPPP PROVIDE A DESCRIPTIN OF INTERIM AND PERMANENT STABILIZATION PRACTICES, AND WHEN THESE STABILIZATION MEASURES WERE INITIATED.

Source

Authoritative
EPA ECHO
Machine
JSON-LD · Markdown