← EPA enforcement cases

RHEIN INTERESTS OF CHARLOTTE, LLC (GRAND PALISADES PARKWAY NORTH)

Administrative - Formal · FY2005 · — · Final Order With Penalty · 159361

Penalty
Cost recovery
Compliance action

Case

Case Number
04-2005-4545
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
Self-disclosure
N

Defendants (3)

Summary

9/30/05 - COMPLAINT ISSUED PROPOSING A PENALTY OF $157,500. 9/30/05 - COMPLAINT FILED, PROPOSING A PENALTY OF $157,500. RESPONDENT FAILED TO COMPLY WITH PART I.A.2 OF THE PERMIT BY FAILING TO IMPLEMENT THE PLAN AS APPROVED AND BY FAILING TO AMEND THE PLAN TO INCLUDE THE EXTRA TEMPORARY BASIN NEAR SEEP BERM G. RESPONDENT FAILED TO COMPLY WITH PART I.B.1 OF THE PERMIT BY FAILING TO INSPECT ALL EROSION AND SEDIMENTATION CONTROL FACILITIES AT LEAST ONCE EVERY SEVEN (7) CALENDAR DAYS AND WITHIN TWENTY-FOUR (24) HOURS AFTER ANY STORM EVENT GREATER THAN O.5 INCHES OF RAN PER TWENTY-FOUR (24) HOUR PERIOD. RESPONDENT FAILED TO COMPLY WITH I.B.2 OF THE PERMIT BY FAILING TO TAKE CORRECTIVE ACTION IMMEDIATELY TO CONTROL THE DISCHARGEE OF SEDIMENTS FROM LEAVING THE DISTURBED LIMITS OF THE FACILITY. RESPONDENT FAILED TO COMPLY WITH PART I.C.1 OF THE PERMIT BY FACILITY TO COMPLY WITH FINAL LIMITATIONS AND CONTROLS AS EVIDENCED BY THE LACK OF MAINTENANCE OF BMPS THROUGHOUT THE FACILITY. RESPONDENT FAILED TO COMPLY WITH PART I.C.2 OF THE PERMIT BY FAILING TO PROVIDE THE OPERATION AND MAINTENANCE NECESSARY TO OPERATE STROM WATER CONTROLS AT OPTIMUM EFFICIENCY AS EVIDENCED BY THE LACK OF MAINTENANCE OF BMPS THROUGHOUT THE FACILITY. RESPONDENT FAILED COMPLY WITH PART II.B.1 OF THE PERMIT WHICH REQUIRES THE PERMITEE TO COMPLY WITH ALL CONDITIONS OF THE PERMIT. RESPONDENT HAS FAILED TO COMPLY WITH ALL CONDITIONS OF THE PERMIT BY FAILING TO CORRECT BMP MAINTENANCE ISSUES, FAILING TO PROVIDE A

Source

Authoritative
EPA ECHO
Machine
JSON-LD · Markdown