# 1488 Land Development
> **Administrative - Formal** · FY2005 · — · Final Order With Penalty
## Case
- **Activity ID:** `161495`
- **Case Number:** 06-2005-2731
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order With Penalty
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- 1488 Land Development (complaint) (settlement)
## Summary

This enforcement action requires that the Respondent complete a $11,000.00 Supplemental Environmental Project (SEP).  The SEP requires that the Respondent restore 1.5 acres of forested wetlands.

---