← EPA enforcement cases

HAVERHILL MA CITY OF

Administrative - Formal · FY2002 · — · Final Order No Penalty · 1643

Penalty
Cost recovery
$10.50M
Compliance action

Case

Case Number
01-2002-0005
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order No Penalty
Multimedia
N
Self-disclosure
N

Defendants (1)

Summary

A DRAFT LONG-TERM CSO CONTROL PLAN WAS SUBMITTED BY HAVERHILL AFTER AGENCIES COMMENT, ADDITIONAL CSOS WERE DISCOVERED. ORDER 02-02 WAS ISSUED TO REQUIRE COMPLETION OF THE CSO PLANNING PROCESS & ENVIRONMENTAL REVIEW TO ADDRESS AGENCIES COMMENTS, AND THE UNPERMITTED CSO DISCHARGES. THE CITY DVAS ORDERED TO IMPLEMENT PHASE I CSO ABATEMENT PROJECTS INCLUDING: INCREASING WWTF WET WEATHER CAPACITY AND BRADFORD-SIDE CSOS STRUCTURAL MODIFICATIONS.

Source

Authoritative
EPA ECHO
Machine