← EPA enforcement cases

MUNDET-HERMETITE, INC.

Judicial · FY1994 · — · Final Order With Penalty · 16834

$90K
Penalty
Cost recovery
Compliance action

Case

Case Number
03-1994-0339
Type
Judicial
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
N
Self-disclosure
N

Defendants (1)

Summary

THE PSD VIOLATION HERE IS BASED ON MHI'S CONSTRUCTION OF LINE NUMBER 8 AT THE FACILITY IN 1988 WHICH CONSTITUTED A PHYSICAL CHANGE TO THE FACILITY (WHICH WAS AN EXISTING MAJOR STATIONARY SOURCE, EMITTING APPROXIMATELY 840 TONS OF VOCS PER YEAR) WHICH RESULTED IN A SIGNIFICANT NET EMISSIONS INCREASE. AS MUNDET-HERMETITE, INC. DID NOT OBTAIN A PSD PERMIT PRIOR TO BEGINNING CONSTRUCTION OF THE MAJOR MODIFI- CATION, IT IS IN VIOLATION OF 40 C.F.R. SECTION 52.21(I)(1).

Source

Authoritative
EPA ECHO
Machine