# AMERIGAS PROPANE, L.P.
> **Administrative - Formal** · FY2006 · — · Final Order With Penalty
## Case
- **Activity ID:** `169173`
- **Case Number:** 04-2006-8015
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order With Penalty
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- AMERIGAS PROPANE, L.P. (complaint) (settlement)
## Summary

2/6/06 - EXPEDITED SETTLEMENT AGREEMENT ISSUED, ASSESSING A PENALTY OF $600, DUE WITHIN 15 DAYS.  

ALLEGED VIOLATIONS:  ON DECEMBER 12, 2005, AN AUTHORIZED REPRESENTATIVE OF THE EPA CONTACTED THE RESPONDENT CONCERNING THE FACT THAT THE RESPONDENT HAD NOT RESUBMITTED THE RISK MANAGEMENT PLAN FOR ITS FACILITY.  THE PLAN WAS DUE FOR RESUBMISSION ON JUNE 9, 2005.  FAILURE TO REVIEW, UPDATE, AND RESUBMIT THE PLAN ON OR BEFORE ITS APPLICABLE DUE DATE IS A VIOLATION OF THE RISK MANAGEMENT PROGRAM REGULATIONS PROMULGATED AT 40 CFR 68.190(b)(1) UNDER SECTION 112(r) OF THE CAA.

---
*Source: [EPA ECHO](https://echo.epa.gov/) · AI Analytics · CC0 1.0*