← EPA enforcement cases

Fenn, Devin (D. Fenn Enterprises)

Administrative - Formal · FY2006 · — · Unilateral Administrative Order Without Adjudication · 173769

Penalty
Cost recovery
Compliance action

Case

Case Number
09-2006-0053
Type
Administrative - Formal
Lead
EPA
Outcome
Unilateral Administrative Order Without Adjudication
Multimedia
Self-disclosure
N

Defendants (2)

Summary

This action is an Administrative Order (AO) requiring Triumph Builders (prime contractor) and Devin Fenn and D. Fenn Enterprises, Inc. (subcontractors) to remove demolition waste from the San Pedro River and to restore the site to pre-disturbance condition. The San Pedro River originates in Mexico and is recognized by scientists, government agencies, and non-governmental organizations as one of the most important environmental assets in the United States. In 2003, Devin Fenn and his company via contract with Triumph Builders were involved in demolition and construction projects near Pomerene, Arizona where large quantities of solid waste were generated. Waste materials including broken concrete, asphalt, metal rebar, soil, PVC pipes, and vegetative debris were trucked to the river and dumped, creating approximately 20 ft by 100 ft of rubble lining along the San Pedro River bankline. Devin Fenn's company was also the contractor responsible for discharges in an earlier enforcement matter involving the San Pedro River, see Kartchner (09-2004-0354). This AO requires Fenn to implement a removal and restoration plan.

Source

Authoritative
EPA ECHO
Machine