# Vistas de Guarbo
> **Administrative - Formal** · FY2006 · — · Final Order With Penalty
## Case
- **Activity ID:** `177260`
- **Case Number:** 02-2006-3409
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order With Penalty
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- Cue and Lopez Contractors (complaint) (settlement)
- Vistas de Guarbo (complaint) (settlement)
## Summary

The site is approximately 5 acres, it has a CES Plan but did not have a construction general permit, it did have some storm water controls and did not have a Storm Water Pollution Prevention Plan.  An Administrative Order was issued for the facility to develop and implement a SWPPP, to submit an NOI, obtain a PErmit and provide information.  As of March 1, 2006, the facility did not comply.

---