# P & W ELECTRIC SUPERFUND SITE (HUNTSVILLE UTILITIES)
> **Administrative - Formal** · FY2006 · — · Final Order With Specified Cost Recovery
## Case
- **Activity ID:** `179430`
- **Case Number:** 04-2006-3763
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order With Specified Cost Recovery
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- HUNTSVILLE UTILITIES (settlement)
## Summary

4/11/06 - AGREEMENT FOR RECOVERY OF PAST RESPONSE COSTS ISSUED.  RESPONDENT:  HUNTSVILLE UTILITIES.  WITHIN 5 BUSINESS DAYS AFTER SETTLING PARTY RECEIVES NOTICE FROM EPA THAT THIS AGREEMENT HAS BEEN SIGNED BY EPA AND APPROVED BY THE ATTORNEY GENERAL OR HIS DESIGNEE, SETTLING PARTY SHALL DEPOSIT $10,000 INTO AN ESCROW ACCOUNT BEARING INTEREST ON COMMERCIALLY REASONABLE TERMS, IN A FEDERALLY-CHARTERED BANK.

---