# Town of Rhinebeck
> **Administrative - Formal** · FY2009 · — · Final Order With Specified Cost Recovery
## Case
- **Activity ID:** `1800010376`
- **Case Number:** 02-2009-2001
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order With Specified Cost Recovery
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- Town of Rhinebeck (settlement)
## Summary

This is a de minimis settlement with the PRP who sent a de minimis amount of hazardous substances to the Consolidated Iron and Metal Site, Newburgh, New York.  The Respondent sent 140,275 lbs of  tracked waste   - scrap materials containing hazardous substances (i.e. PCBs and VOCs) to the Site, which when processed at the Site, caused a release of hazardous substances.  The Respondent is paying its share of all past and estimated future costs, plus a premium.

---