Summary

This Administrative Compliance Order (ACO) addressed EPA?s findings that Asbestos Mold and Services Corp (Asbestos Mold) failed to comply with the notification requirements of the Asbestos NESHAP. The ACO requires Asbestos Mold to wait ten working prior to starting all future demolitions/renovations that are subject to the asbestos NESHAP.