# Ivory Homes
> **Judicial** · FY2009 · — · Final Order With Penalty
## Case
- **Activity ID:** `1800029232`
- **Case Number:** 08-2009-0213
- **Type:** Judicial
- **Lead:** EPA
- **Outcome:** Final Order With Penalty
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- Ivory Homes (complaint) (settlement)
## Summary

The consent decree requires Ivory Homes to obtain all required permits, develop site-specific pollution prevention plans for each construction site, conduct additional site inspections beyond those required by stormwater regulations, and document and promptly correct any problems. Ivory must properly train construction managers and contractors on stormwater requirements and designate trained staff for each site.

---