# PONTOTOC UNION LEE ALLIANCE AND L& T CONSTRUCTION, INC. - BLUE SPRINGS NORTH LOOP
> **Administrative - Formal** · FY2009 · — · Unilateral Administrative Order Without Adjudication
## Case
- **Activity ID:** `1800040554`
- **Case Number:** 04-2009-4807
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Unilateral Administrative Order Without Adjudication
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- L&T CONSTRUCTION, INC. (settlement)
- PONTOTOC UNION LEE ALLIANCE (settlement)
## Summary

10/6/2009 - ADMINISTRATIVE ORDER ISSUED. ORDER STATES: RESPONDENT FAILED TO COMPLY WITH THE MDEQ PERMIT, AND FOR DISCHARGES NOT AUTHORIZED BY THE PERMIT. IN VIOLATION OF CWA SECTIONS 301 AND 402.

---