# Barnegat Development, Inc.
> **Administrative - Formal** · FY2010 · — · Unilateral Administrative Order Without Adjudication
## Case
- **Activity ID:** `1800074160`
- **Case Number:** 02-2010-3020
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Unilateral Administrative Order Without Adjudication
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- Barnegat Development, Inc. (settlement)
## Summary

Respondent owns a 30.4-acre residential development construction site in Barnegat, NJ.  The facility had a permit but its Stormwater Pollution Prevention Plan, records of site inspections and annual reports were unavailable.  Storm water BMPs required maintenance and/or implementation.

---