# UPPER ALLEGHENY JOINT SEWER AUTHORITY, ET. AL.
> **Administrative - Formal** · FY2010 · — · Final Order No Penalty
## Case
- **Activity ID:** `1800074220`
- **Case Number:** 03-2010-0086
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order No Penalty
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- BRACKENRIDGE BOROUGH (complaint) (settlement)
- BUFFALO TOWNSHIP (complaint) (settlement)
- EAST DEER TOWNSHIP (complaint) (settlement)
- FAWN TOWNSHIP (complaint) (settlement)
- HARRISON TOWNSHIP (complaint) (settlement)
- TARENTUM BOROUGH (complaint) (settlement)
- UPPER ALLEGHENY JOINT SEWER AUTHORITY (complaint) (settlement)
## Summary

UPPER ALLEGHENY IS IN VIOLATION OF ITS NPDES PERMIT REQUIREMENT TO CONTINUE IMPLEMENTATIONOF THE NMCS AND TO DEVELOP AND IMPLEMENT AN LTCP.   UPPER ALLEGHENY CLAIMED INABILITY TO DEVELOP THE LTCP DUE TO LACK OF COOPERATION FROM UNPERMITTED SATELLITE SYSTEMS.   EPA HAS ORDERED ALL RESPONDENTS TO WORK TOGETHER SO THE LTCP CAN BE DEVELOPED.

---
*Source: [EPA ECHO](https://echo.epa.gov/) · AI Analytics · CC0 1.0*