← EPA enforcement cases

DENZIL BOWMAN WASTEWATER TREATMENT PLANT

Administrative - Formal · FY2010 · — · Final Order With Penalty · 1800083518

Penalty
Cost recovery
Compliance action

Case

Case Number
04-2010-8005
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
Self-disclosure
N

Defendants (1)

Summary

3/11/2010 - EXPEDITED SETTLEMENT AGREEMENT ISSUED, ASSESSING A PENALTY OF $1000. RESPONDENT SHALL MAKE PAYMENT WITHIN FIFTEEN DAYS. EPA ALLEGES THAT THE RESPONDENT VIOLATED THE ACT'S CHEMICAL ACCIDENT PREVENTION PROGRAM WHEN RESPONDENT DID NOT PROVIDE THAT: IT HAS REVIEWED, UPDATED AND SUBMITTED ITS RISK MANAGEMENT PLAN (RMPlan) TO EPA AT LEAST EVERY FIVE YEARS AS REQUIRED BY 40 CFR SECTION 68.190(b)(1). THE RESPONDENT RMPlan WAS DUE FOR ITS FIVE YEAR REVIEW, UPDATE AND RESUBMISSION ON OR BEFORE JUNE 21, 2009. AS OF DECEMBER 10, 2009, RESPONDENT HAD NOT UPDATED AND RESUBMITTED ITS RMPlan.

Source

Authoritative
EPA ECHO
Machine