# U S DEPARTMENT OF THE NAVY
> **Administrative - Formal** · FY1998 · — · Final Order With Penalty
## Case
- **Activity ID:** `18310`
- **Case Number:** 03-1998-0403
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order With Penalty
- **Penalty assessed:** $1K
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** Y
## Defendants
- U S DEPARTMENT OF THE NAVY (complaint) (settlement)
## Summary

DURING MULTI-MEDIA INSPECTION OF FACILITY IN JULY 1997, EPA  INSPECTOR DISCOVERED THAT THE ATG RELEASE DETECTION SYSTEM   ON TANKS 295D AND 833B WERE NOT FUNCTIONING PROPERLY AND     THEREFORE NO RELEASE DETECTION WAS BEING PERFORMED FOR       THESE TANKS.  THE INSPECTOR ALSO DISCOVERED THAT TANK 830C   HAD TWO FILL LINES BUT ONLY ONE FILL LINE HAD THE REQUIRED   SPILL PREVENTION EQUIPMENT.

---