UNILATERAL ADMINISTRATIVE ORDER PURSUANT TO SECTION 106 OF CERCLA TO FOURTEEN PARTIES WHICH REQUIRE THAT THEY PERFORM THE REMEDIAL ACTION OUTLINED IN THE RECORD OF DECISION (ROD) FOR THE SITE WHICH WAS ISSUED ON JUNE 29, 1990. THE ROD REQUIRED INSTALLATION OF A WATER LINE AND CONSTRUCTION OF A CAP OVER THE
LANDFILL AREA. EPA HAS DESIGNED AND CONSTRUCTED THE WATERLINE AND APPROVED A FINAL LANDFILL CAP DESIGN ON FEBRUARY 5, 1993. THIS UAO REQUIRES THE PARTIES NAMED TO INSTALL THE CAP PURSUANT TO THE APPROVED DESIGN.
ON JULY 23, 2003, THIS ACTION IS THE ISSUANCE OF AMENDMENT TO A UNILATERAL ADMINISTRATIVE ORDER ( UAO AMENDMENT ) ISSUED PURSUANT TO SECTION 106 OF THE CERCLA.., WHICH REQUIRES TEN (10 PARTIES TO FINANCE AND PERFORM REMEDIAL RESPONSE ACTIVITIES SET FORTH IN THE JULY 2, 2003 AMENDMENT TO THE ROD FOR OU 1