# PLAZA MATERIALS CORP
> **Judicial** · FY1983 · — · Final Order With Penalty
## Case
- **Activity ID:** `1882`
- **Case Number:** 02-1983-0017
- **Type:** Judicial
- **Lead:** EPA
- **Outcome:** Final Order With Penalty
- **Penalty assessed:** $18K
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** N
## Defendants
- PLAZA MATERIALS CORP (complaint) (settlement)
## Summary

THIS CASE PROPOSES FILING A CIVIL ENFORCEMENT ACTION PUR-  SUANT TO CAA 113(B), 42 USC 7413(B), AGAINST PLAZA MATERI-   ALS CORPORATION ( PLAZA  OR  THE CO. ) FOR ITS VIOLATIONS OF PART 212 OF TITLE 6 NYCRR.  THIS REGULATION IS DESIGNED TO   LIMIT THE EMISSION OF PARTICULATE MATTER INTO THE ATMOSPHERE BY REQUIRING, INTER ALIA, THAT THE OWNERS OR OPERATORS OF    INDUSTRIAL PROCESSES PREVENT VISIBLE EMISSIONS WITH AN OPA-  CITY EXCEEDING 20%.  THE REGULATION IS PART OF THE SIP.        TITLE 6 NYCRR 212.7 APPLIES TO THE OWNER OR OPERATOR OF    PROCESS AND EXHAUST &/OR VENTILATION SYSTEMS.  PLAZA OWNS &  OPERATES AN ASPHALT PLANT & ASSOCIATED ROCK CRUSHING OPERA-  TION AT ITS SUFFERN, NY LOCATION.  THESE ARE PROCESS SYSTEMS WITHIN THE MEANING OF 6 NYCRR PART 212; IN ADDITION, THERE   ARE SEVERAL EMISSION POINTS ON THE PLANT WHICH CONSTITUTE    VENTILATION SYSTEMS WITHIN THE MEANING OF THE REGULATION.      BASED ON AN INSPECTION BY AN EPA ENGINEER ON 6/17/82, EPA  ISSUED A  NOV , INDEX NO. 20239, PURSUANT TO CAA/113(B), 42  USC 7413(A).  THE NOTICE CITED THE CO. FOR VIOLATING 6 NYCRR 212.7 BY ALLOWING EMISSIONS SIGNIFICANTLY EXCEEDING 20%      OPACITY TO LEAK FROM THE ASPHALT PLANT & TO EMANATE FROM THE BUILDING WHICH HOUSES THE CRUSHER.                             AN INSPECTION ON 11/2/83 REVEALED THAT THE SAME VIOLATIONS PERSISTED, & HAD ACTUALLY BECOME SEVERELY AGGRAVATED.  EPA   REGION II SEEKS THE EXPEDITIOUS INITIATION OF A CIVIL ENFOR- CEMENT ACTION AGAINST PLAZA FOR INJUNC

---
*Source: [EPA ECHO](https://echo.epa.gov/) · AI Analytics · CC0 1.0*