In re: Mirant Potomac River LLC

Administrative - Formal · FY2006 · — · — · 200002861

Penalty
Cost recovery
Compliance action

Case

Case Number
03-2006-0163
Type
Administrative - Formal
Lead
EPA
Outcome
Multimedia
Self-disclosure
N

Defendants (1)

Summary

In August 2005, a dispersion modeling analysis showed that Mirant's Potomac River Generating Station (PRGS) was causing or contributing to significant exceedances of the NAAQS. EPA sent a Notice of Violation citing Mirant's failute to immediately shut down the PRGS. EPA approved State Implementation Plan and theefore federally enforceable. EPA negotiated an Administrative Complaince Order. this Order was signed on June 1, 2006