# B.F. GOODRICH/AIRCO SITE
> **Judicial** · FY1988 · — · Final Order With Specified Cost Recovery
## Case
- **Activity ID:** `20364`
- **Case Number:** 04-1988-0065
- **Type:** Judicial
- **Lead:** EPA
- **Outcome:** Final Order With Specified Cost Recovery
- **Penalty assessed:** $0
- **Cost recovery:** $389K
- **Compliance action $:** —
- **Multimedia (multi-env):** N
## Defendants
- B.F. GOODRICH COMPANY (complaint) (settlement)
- BOC GROUP, INC. (complaint) (settlement)
## Summary

THE REGION, WITH ASSISTANCE FROM EPA HEADQUARTERS, HAS     COMPLETED CONSENT DECREE NEGOTIATIONS WITH THE B.F. GOODRICH COMPANY AND THE BOC GROUP, INC., FOR THE REMEDIAL DESIGN     AND REMEDIAL ACTION ( RD/RA ) AT THE B.F. GOODRICH/AIRCO     NPL SITE IN CALVERT CITY, KENTUCKY.  THE B.F. GOODRICH       COMPANY ( BFG ) AND THE BOC GROUP, INC. ( BOC ) HAVE SIGNED  THE CONSENT DECREE.                                            UNDER THER TERMS OF THE DECREE, BFG AND BOC WILL IMPLE-    MENT THE REMEDY SELECTED BY EPA AS SET OUT IN THE TWO        RECORDS OF DECISION.  EPA HAS ISSUED TWO RODS BECAUSE THE    B.F. GOODRICH/AIRCO SITE IS ACTUALLY TWO SEPARATE NPL SITES. SINCE THE TWO SITES ARE LOCATED DIRECTLY ADJACENT TO EACH    OTHER AND SHARE A SOMEWHAT COMMON HISTORY, EPA DECIDED THAT  IT WOULD BE MORE COST EFFECTIVE AND TECHNOLOGICALLY          EXPEDIENT TO CONDUCT ONE REMEDIAL INVESTIGATION AND          FEASIBILITY STUDY FOR THE SITES.  THE REGION REFERS TO THE   SITES AS THE B.F. GOODRICH/AIRCO SITE.  BFG AND BOC          (FORMERLY KNOW AS AIRCO) JOINTLY CONDUCTED THE RI/FS.

---
*Source: [EPA ECHO](https://echo.epa.gov/) · AI Analytics · CC0 1.0*