# SANGAMO WESTON/12 MILE CREEK/LAKE HARTWELL OU1
> **Judicial** · FY1992 · — · Final Order With Specified Cost Recovery
## Case
- **Activity ID:** `20754`
- **Case Number:** 04-1992-0021
- **Type:** Judicial
- **Lead:** EPA
- **Outcome:** Final Order With Specified Cost Recovery
- **Penalty assessed:** $0
- **Cost recovery:** $743K
- **Compliance action $:** —
- **Multimedia (multi-env):** N
## Defendants
- SCHULMBERGER IND. INC. (complaint) (settlement)
## Summary

--CD ENTERED 12/03/92--                                      THE SANGAMO WESTON/TWELVE MILE CREEK/LAKE HARTWELL PCB CONT. SUPERFUND SITE, OPERABLE UNIT NO. 1, CONSENT DECREE PROVIDES FOR THE FINANCING AND IMPLEMENTATION OF RD/RA BY             SCHLUMBERGER INDUSTRIES, INC. (SII).  IN ADDITION, THE CD    REQUIRES SII TO PAY THE AMOUNT OF $792,796.65 IN PAST COST   RECOVERY ASSIGNED TO OPERABLE UNIT NO.1, AND ALL FUTURE      OVERSIGHT COSTS FOR RD/RA.  AS OF SEPTEMBER 15, 1992, THE CD WAS LODGED BUT IT HAS NOT BEEN ENTERED.  CASE FILED IN U.S.  DISTRICT COURT FOR S.C., ANDERSON DIVISION; CIVIL NO.        8-92-1097-20.

---
*Source: [EPA ECHO](https://echo.epa.gov/) · AI Analytics · CC0 1.0*