← EPA enforcement cases

NATIONAL SOUTHWIRE ALUMINUM COMPANY (NSA)

Judicial · FY1993 · — · Final Order With Specified Cost Recovery · 20930

$0
Penalty
$408K
Cost recovery
Compliance action

Case

Case Number
04-1993-1340
Type
Judicial
Lead
EPA
Outcome
Final Order With Specified Cost Recovery
DOJ Docket
90-11-3-1148
Multimedia
N
Self-disclosure
N

Defendants (1)

Summary

THE SITE IS LOCATED IN HAWESVILLE, HANCOCK COUNTY, KENTUCKY. NATIONAL SOUTHWIRE ALUMINUM COMPANY ( NSA ) OPERATES AN ACTIVE ALUMINUM REDUCTION FACILITY AT THE SITE. FOUR WASTE POINDS ARE ON THE SITE. NSA DISPOSED OF SPENT ALUMINUM POTLINERS, PAINT FILERS, AND CALCIUM FLUORIDE INTO THE PONDS. IN 1979, NSA LEARNED THAT CYANIDES, METALS, AND FLUORIDES WERE LEACHING FROM THE POINDS AND INTO THE GROUNDWATER. THE PA/SI ALSO INDICATES THAT THE SOIL IS CONTAMINATED WITH PCBS. IN OCTOBER 1992, NSA AGREED TO PERFORM THE RI/FS UNDER AN ADMINISTRATIVE ORDER ON CONSENT WITH EPA. NSA IS ANXIOUS TO BEGIN RA CONSTRUCTION FOR CONTAINMENT OF TWO UNDERGROUND WATER PLUMES, AS DESCRIBED IN THE INTERIM ACTION RECORD OF DECISION ISSUED ON FEBRUARY 19, 1993. NSA HAS ALREADY PURCHASED MUCH OF THE PUMP AND TREAT SYSTEM NECESSARY FOR THE INTERIM REMEDIAL ACTION. THE PRN WAS SENT TO OBTAIN DOJ AND HEADQUARTERS CONCURRENCE.

Source

Authoritative
EPA ECHO