# DIAMOND SHAMROCK
> **Judicial** · FY1994 · — · Final Order With Specified Cost Recovery
## Case
- **Activity ID:** `21056`
- **Case Number:** 04-1994-0266
- **Type:** Judicial
- **Lead:** EPA
- **Outcome:** Final Order With Specified Cost Recovery
- **Penalty assessed:** —
- **Cost recovery:** $388K
- **Compliance action $:** $461K
- **Multimedia (multi-env):** N
## Defendants
- HENKEL CORPORATION (complaint) (settlement)
## Summary

ON MARCH 3, 1994 A MINI-LITIGATION REPORT WAS FORWARDED TO   HEADQUARTERS FOR THE RD/RA NEGOTIATIONS ON THE DIAMOND       SHAMROCK LANDFILL SITE IN CEDARTOWN, POLK COUNTY, GEORGIA.   THE SITE WAS INCLUDED IN THE NPL IN JANUARY 1987.  IN 1972,  APPROXIMATELY 1500 GALLONS OF MTALL OIL PITCH, FATTY ACIDS,  GLYCERIDES AND OIL WERE BURIED IN TRENCHES AT THE SITE.      HENKIL CORP. THE CURRENT OWNER/OPERATOR ENTERED INTO AN AOC  FOR REMOVAL AND THEREAFTER AN AOC AGREEING TO CONDUCT TH     RI/FS.  CURRENTLY THERE ARE TWO PRP'S, HENKIL CORPORATION    AND OCCIDENTAL CHEMICAL CORPORATION, THE SUCESSOR TO THE     OWNER/OPERATOR OF THE SITE AT THE TIME WASTE WAS BURIED.     RA'S PERFERRED REMEDY WOULD CALL FOR:                            1) DEED RESTRICTIONS                                         2) SITE ACCESS RESTRICTIONS                                  3) GROUNDWATER AND CEDAR CREEK SURFACE WATER MONITORING      4) FIVE YEAR REVIEWS                                         5) CONTINUED GROUNDWATER MONITORING TO BE APPROVED BY    EPA                                                          THE ROD IS EXPECTED TO BE SIGNED DURING THE FIRST WEEK OF    MAY, 1994.

---
*Source: [EPA ECHO](https://echo.epa.gov/) · AI Analytics · CC0 1.0*