# ALLSTEEL, INC.
> **Judicial** · FY1994 · — · Final Order With Penalty
## Case
- **Activity ID:** `21067`
- **Case Number:** 04-1994-0286
- **Type:** Judicial
- **Lead:** EPA
- **Outcome:** Final Order With Penalty
- **Penalty assessed:** $50K
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** N
## Defendants
- ALLSTEEL, INC. (complaint) (settlement)
## Summary

REFERRAL FOR INJUNCTIVE RELIEF AND CIVIL PENALTIES.          DEFENDANT VIOLATED CLEAN AIR ACT AND TENESSEE SIP BY         BEGINNING CONSTRUCTION OF MAJOR VOC SOURCE WITHOUT PSD       PERMITS.  DEFENDANT CONTINUED TO VIOLATE ACT AND SIP BY      CONSTRUCTING SOURCE PURSUANT TO INVALID PERMITS THAT DID NOT APPLY BACT.  DEFENDANT VIOLATED AN EPA ADMINISTRATIVE ORDER  BANNING CONSTRUCTION.

---
*Source: [EPA ECHO](https://echo.epa.gov/) · AI Analytics · CC0 1.0*