SUMMIT RESOURCES-BANKRUPTCY

Judicial · FY1994 · — · Final Order With Specified Cost Recovery · 21114

Penalty
$62K
Cost recovery
Compliance action

Case

Case Number
04-1994-0418
Type
Judicial
Lead
EPA
Outcome
Final Order With Specified Cost Recovery
Multimedia
N
Self-disclosure
N

Defendants (2)

Summary

EPA CONDUCTED FUND-LEAD REMOVAL ON SITE AND EXPENDED APPROXIMATELY $2 MILLION. ONE PRP, SUMMIT, ON JUNE 28, 1994, VOLUNTARILY FILED FOR CHAPTER 7 BANKRUPTCY. BAR DATE IS NOVEMBER 1, 1994. THE PURPOSE OF THIS BANKRUPTCY REFERRAL IS TO REQUEST THAT DOJ FILE A PROOF OF CLAIM ON EPA'S BEHALF BEFORE THE BAR DATE.