# BEAUNIT CORP. CIRCULAR KNIT & DYEING PLANT SUPERFUND SITE
> **Judicial** · FY1995 · — · Final Order With Specified Cost Recovery
## Case
- **Activity ID:** `21197`
- **Case Number:** 04-1995-0056
- **Type:** Judicial
- **Lead:** EPA
- **Outcome:** Final Order With Specified Cost Recovery
- **Penalty assessed:** $0
- **Cost recovery:** $1
- **Compliance action $:** —
- **Multimedia (multi-env):** N
## Defendants
- COLLINS & AIKMAN PRODUCTS CO. (complaint) (settlement)
- CONTINENTAL ASSURANCE COMPANY (complaint) (settlement)
- EL PASO NATURAL GAS COMPANY (complaint) (settlement)
- PEPSI CO, INC. (complaint) (settlement)
- WILSON SPORTING GOODS (complaint) (settlement)
## Summary

PROPOSED PLAN OF REMEDIAL ACTION                             THE REMEDIAL DESIGN AND REMEDIAL ACTION (RD/RA) WILL ADDRESS THE HAZARDS POSED BY THE CONTAMINATION IN THE GROUNDWATER    AND SURFACE SOILS.  THE PROPOSED PLAN FOR REMEDIAL ACTION    INVVOLVES NATURAL ATTENUATION OF GROUNDWATER, GRADING,       DRAINAGE CONTROL AND A PERMEABILITY CAP OF THE SURFACE       SOILS, MONITORING OF GROUNDWATER, SURFACE WATER AND          ASSOCIATED SEDIMENTS, AND LAND USE AND DEED RESTRICTIONS.    SPECIFICALLY, THE REMEDIAL ACTION WILL UTILIZE A MONITORING  PROGRAM FOR GROUNDWATER, STREAM SURFACE WATER AND STREAM     SEDIMENTS TO PROVIDE A METHOD FOR IDENTIFYING ANY CHANGES IN THE SITE CONDITIONS.  GROUNDWATER SAMPLES WILL BE COLLECTED  FROM SIX OF THE MONITORING WELLS AND FROM THREE SURFACE      WATER AND SEDIMENT SAMPLING LOCATIONS.  SAMPLES FROM THESE   LOCATIONS WILL BE COLLECTED AND ANALYZED SEMI-ANNUALLY FOR   THE FIRST TWO YEARS AND ANNUALLY FOR THREE YEARS THEREAFTER. THE CONTAMINATED SOIL WILL BE ADDRESSED BY PLACEMENT OF A    PERMEABILITY CAP OVER THE SOILS CONTAINED IN THE FENCED      AREA.  PRIOR TO THE PLACEMENT OF THIS CAP, A CONTAMINATED    HOT SPOT OF SOIL OUTSIDE THE FENCED AREA WILL BE EXCAVATED   AND ADDED TO THE SOILS WITHIN THE FENCE.  THIS  HOT SPOT  IS LOCATED ALONG THE AREA WHERE THE PIPELINE BETWEEN THE        MANUFACTURING FACILITY AND WASTEWATER TREATMENT PLANT WAS    LOCATED.  THE SITE WILL BE GRADED, THE LAGOON WILL BE        BACKFILLED, AND A CAP WILL BE PLACED

---