← EPA enforcement cases

MASONITE CORP./CENTRAL HARDBOARD DIVISION

Administrative - Formal · FY1995 · — · Unilateral Administrative Order Without Adjudication · 21504

$0
Penalty
$0
Cost recovery
Compliance action

Case

Case Number
04-1995-0544
Type
Administrative - Formal
Lead
EPA
Outcome
Unilateral Administrative Order Without Adjudication
Multimedia
N
Self-disclosure
N

Defendants (1)

Summary

9/29/95 - 3013 ORDER ISSUED. 7/19/2018 - LETTER FROM EPA TO RESPONDENT STATING, THE FINAL INVESTIGATIVE WORK REQUIRED UNDER THE AO CONSISTEND OF AN ECOLOGICAL RISK ASSESSMENT (ERA) WHICH BEGAN IN JULY 2013. THE ERA ADDRESSED THE SOUTH FIELD AND POND 1 (SOLID WASTEMENT MGMT UNITS (SWMUs) 10 AND 11). THE FINAL RESULTS OF THIS ERA WERE SUBMITTED TO EPA ON OCT 6, 2017. EPA HAS CONCLUDED THAT, GIVEN THE AVAILABLE INFO, THERE DOES NOT APPEAR TO BE APPRECIABLE RISK POSED BY THE METALS EXAMINED IN THIS ASSESSMENT TO BIRDS OR MAMMALS THAT MIGHT FEED ON THE POND 1 AND SOUTH FIELD AREAS... ...THE ERA WAS THE LAST PORTION OF THE ASSESSMENT WORK REQUIRED UNDER THE AO. SEVERAL AREAS OF THE MASONITE FACILITY REMAIN SUBJECT TO REMEDIATION AND MONITORING UNDER THE AUTHORITY OF THE MS DEPT OF ENVIRONMENTAL QUALITY (MDEQ). TERMINATION OF THIS EPA AO DOES NOT IMPACT ANY REMAINING WORK OR ACTIVITIES, INCLUDING ANY INSTITUTIONAL CONTROLS, REQUIRED BY EXISTING ORDER WITH MDEQ...

Source

Authoritative
EPA ECHO
Machine
JSON-LD · Markdown