# Diamondback Motorcross (SB) et al.
> **Administrative - Formal** · FY2010 · — · Final Order With Penalty
## Case
- **Activity ID:** `2200014971`
- **Case Number:** 02-2010-3316
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order With Penalty
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- Diamondback Motorcross (SB) (complaint) (settlement)
- Weldon House (SB) (complaint) (settlement)
## Summary

Respondent is a construction site greater than 5 acres and performed construction activities for 8 months without permit coverage.  An ESO issued to Respondents undergoing construction activities for 5 months without a SPDES construction stormwater permit.

---