# Elam Construction, Inc.
> **Administrative - Formal** · FY2010 · — · Final Order No Penalty
## Case
- **Activity ID:** `2200015657`
- **Case Number:** 08-2010-0174
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order No Penalty
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- 4B Land & Livestock (complaint) (settlement)
- Elam Construction (complaint) (settlement)
- Scott and Sheila Brennise (complaint) (settlement)
## Summary

This Administrative Order for Compliance is issued to Elam Construction, Scott and Sheila Brennise and 4B Land and Livestock for the unauthorized discharge of dredged and/or fill material into wetlands adjacent to the Yampa River, which is a navigable-in-fact tributary to the Green River. This discharge occurred in conjunction with gravel mining operations on property located in Moffat County, CO.

---
*Source: [EPA ECHO](https://echo.epa.gov/) · AI Analytics · CC0 1.0*