← EPA enforcement cases

Betteroads Asphalt Corporation

Administrative - Formal · FY2010 · — · Unilateral Administrative Order Without Adjudication · 2200015781

Penalty
Cost recovery
Compliance action

Case

Case Number
02-2010-3122
Type
Administrative - Formal
Lead
EPA
Outcome
Unilateral Administrative Order Without Adjudication
Multimedia
Self-disclosure
N

Defendants (1)

Summary

THIS INDUSTRIAL FACILITY WAS FOUND IN VIOLATION OF SECTION 402 FOR ITS FAILURE TO COMPLY WITH THE REQUIREMENTS OF THE PERMIT. THE ORDER REQUIRES THE SUBMITTAL OF A COMPLIANCE PLAN, DEVELOP STANDARD OPERATING PROCEDURES (SOPs) FOR RAINFALL COLLECTION, MONITORING, AND REPORTING OF THE STORM WATER.

Source

Authoritative
EPA ECHO
Machine
JSON-LD · Markdown