← EPA enforcement cases

REDWING/SARALAND (Referral f/Cost Rec. and Response Actions)

Judicial · FY1999 · — · Final Order With Specified Cost Recovery · 23002

Penalty
Cost recovery
Compliance action

Case

Case Number
04-1999-0087
Type
Judicial
Lead
EPA
Outcome
Final Order With Specified Cost Recovery
DOJ Docket
90-11-2-653/1
Multimedia
N
Self-disclosure
N

Defendants (7)

Summary

THIS IS A 106/107 CIVIL ACTION AGAINST THE DEFENDANTS TO OBTAIN REIMBURSEMENT FOR RESPONSE COSTS INCURRED BY EPA AT REDWING/SARALAND SUPERFUND SITE. EPA CONDUCTED SEVERAL REMOVAL ACTIONS AT THE SITE TO REMOVE CONTAMINANTS FROM THE SOIL. EPA ALSO SEEKS A COURT ORDER REQUIRING THAT THE PRPS PERFORM ADDITIONAL RESPONSE ACTIONS AT THE SITE.