← EPA enforcement cases

RILEY BATTERY SUPERFUND SITE

Judicial · FY1999 · — · Final Order With Penalty & Specified Cost Recovery · 23272

Penalty
Cost recovery
Compliance action

Case

Case Number
04-1999-0400
Type
Judicial
Lead
EPA
Outcome
Final Order With Penalty & Specified Cost Recovery
DOJ Docket
90-11-3-06964
Multimedia
N
Self-disclosure
N

Defendants (1)

Summary

THIS IS A COST RECOVERY REFERRAL FOR THE REIMBURSEMENT OF REMOVAL RESPONSE COSTS ASSOCIATED WITH THE SITE. THE SITE WAS CONTAMINATED WITH LEAD AND A PRP-LEAD REMOVAL WAS PERFORMED UNDER AN AOC. THE AOC ALSO REQUIRED THE REIMBURSEMENT OF ALL COSTS ASSOCIATED WITH THE SITE. THE PRP, TROUTMAN LAND INVESTMENTS, IN VIOLATION OF THE AOC, HAS NOT REIMBURSED EPA'S RESPONSE COSTS.