COMMONWEALTH OF MASSACHUSETTS DIVISION OF CAPITAL PLANNING

Judicial · FY1991 · — · Final Order With Penalty · 238

$50K
Penalty
Cost recovery
$1.50M
Compliance action

Case

Case Number
01-1991-0018
Type
Judicial
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
N
Self-disclosure
N

Defendants (3)

Summary

THE PROPOSED DEFENDANTS FILLED WETLANDS IN ORDER TO CONSTRUCT A CORRECTIONAL FACILITY, INCLUDING ACCESS ROADS, AND RELATED STRUCTURES, IN DARTMOUTH, MASSACHUSETTS. THE FILLED AREA CONSTITUTES APPROXIMATELY 11.56 ACRES. THE FILLING BEGAN IN SEPTEMBER, 1988 AND WAS COMPLETED IN MAY, 1990. THE PROPOSED DEFENDANTS FILLED THE WETLANDS WITHOUT OBTAINING A PERMIT FROM THE ARMY CORPS OF ENGINEERS AND WITHOUT QUALIFYING FOR EXEMPTIONS.

Source

Authoritative
EPA ECHO
Machine
JSON-LD · Markdown