JDN DEVELOPMENT COMPANY, INC.

Administrative - Formal · FY2001 · — · Unilateral Administrative Order Without Adjudication · 24367

Penalty
Cost recovery
$0
Compliance action

Case

Case Number
04-2001-0130
Type
Administrative - Formal
Lead
EPA
Outcome
Unilateral Administrative Order Without Adjudication
Multimedia
N
Self-disclosure
N

Defendants (1)

Summary

ORDER ISSUED 10/11/2000. RESPONDENT FAILED TO INSTALL AND MAINTAIN PROPER SILATION AND EROSION CONTROL MEASURES AT THE DISCHARGE ARE DURING PERMITTED CONSTRUCTION AND FILL ACTIVITY, WHICH LED TO DOWNSTREAM IMPACTS TO STREAMS AND LAKE LUCERNE, FAILED TO OBTAIN FILL MATERIAL USED AT THE DISCHARGE AREA THAT WAS FREE OF FOREIGN MATERIAL. IN VIOLATION OF THE CWA SECTIONS 404 & 301(A). REDS NO: 2001 040 6VC 0ZH QKV