# JONES&LAUGHLIN/YNGSTWN SHEET&TUBE
> **Judicial** · FY1982 · — · Final Order With Penalty
## Case
- **Activity ID:** `25179`
- **Case Number:** 05-1982-0066
- **Type:** Judicial
- **Lead:** EPA
- **Outcome:** Final Order With Penalty
- **Penalty assessed:** $4.00M
- **Cost recovery:** $0
- **Compliance action $:** —
- **Multimedia (multi-env):** N
## Defendants
- JONES & LAUGHLIN INDUSTRIES INC. (complaint) (settlement)
- JONES & LAUGHLIN STEEL CORP. (complaint) (settlement)
- LTV CORP. (complaint) (settlement)
## Summary

NATURE OF THE CASE:                                             CONTEMPT ACTION TO ENFORCE REQUIREMENTS OF CD.            CAUSE OF ACTION:                                                CO HAS VIOL'D ONE OR MORE OF THE CD REQUIREMENTS IN RE- SPECT TO COKE BATTERIES 4 & 9, & BLAST FURNACE CAST HOUSES   H-1, H-2, & H-4.                                               PROPOSED REMEDY:                                                REVISED COMPLIANCE SCHED STIPULATED & CIVIL PLTY'S.       NATIONALLY SIGNIFICANT ISSUES:                                  THE ISSUES INVOLVED IN THIS CONTEMPT ACTION MAY BE RE-  SOLVED PURSUANT TO THE SSO PROCESS.                            CIVIL PENALTIES FOR COMBINED INDIANA, OHIO, AND PENN            C.D.'S:  PAY W/IN 10 DAYS OF LAST OF THREE C.D.'S       ENTERED $2MILLION TO U.S.A., .5MILLION TO PA, .5MILLION TO   ALLEGHENY CTY, PA                                                 OR                                                           PAY INTO ESCROW ACCT W/IN 30 DAYS FOLLOWING ENTRY OF    FIRST ORDER.                                                      PAY W/IN 6MTHS. OF LAST OF THREE C.D.'S ENTERED AN      ADDITIONAL $1MILLION.

---