JONES&LAUGHLIN/CAMPBELL WORKS

Judicial · FY1982 · — · Final Order With Penalty · 25182

$4.00M
Penalty
$0
Cost recovery
Compliance action

Case

Case Number
05-1982-0070
Type
Judicial
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
N
Self-disclosure
N

Defendants (1)

Summary

NATURE OF THE CASE: CONTEMPT ACTION TO ENFORCE REQUIREMENTS OF CONSENT DECREES. CAUSE OF ACTION: COMPANY HAS VIOLATAED CONTROL SCHEDULES FOR THEIR COKE BATTERIES #7 & #9 FOR PUSHING CONTROLS BY FAILURE TO PLACE PURCHASE ORDERS AND INSTALL EQUIPMENT. FINAL COMPLIANCE WITH STANDARDS HAS NOT BEEN DEMONSTRATED. ALSO, COMBUSTION STACK CONTROLS HAVE NOT BEEINSTALLED AT BATTERY #9 AND FINAL COMPLIANCE HAS NOT BEEN DEMONSTRATED. PROPOSED REMEDY: INITIATION OF CONTEMPT PROCEEDINGS REQUESTS THE COURT TO ORDER EXPEDITIOUS COMPLIANCE AND AWARD STIPULATED PENALITES FOR DECREE VIOLATION.