← EPA enforcement cases

Social Springs (South) Water System

Administrative - Formal · FY2011 · — · Final Order No Penalty · 2600029206

Penalty
Cost recovery
Compliance action

Case

Case Number
06-2011-1298
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order No Penalty
Multimedia
Self-disclosure
N

Defendants (1)

Summary

AO issued for failure to comply with the PWS monitoring requirements for Stage 2 DBPR. In July 2011, Respondent is required to conduct standard monitoring for TTHM and HAA5. Within 30 days of receiving the final monitoring results, Respondent shall provide EPA an IDSE Report.

Source

Authoritative
EPA ECHO
Machine
JSON-LD · Markdown